The situation with coal production and use in the UK is changing. There are no new opencast mines proposed; only one proposed opencast coal extension and one existing opencast extraction site. However there are three new underground coal mine applications or extensions proposed and there was an increase in coal use in power stations between 2020 and 2021.

Coal use in power stations

As you can see from the image above coal use in power stations has dropped dramatically since 2012, when 43% of electricity in the UK grid was produced from coal combustion, to just 1.72% in 2020.

Coal use hit a record low in 2020 supplying 253 TWh to the grid, and increased slightly the following year to 267 TWh, as the economy ramped back up from covid-19. (The data for 2022 is only for the first fortnight of the year). Thanks to MyGridGB for this data.

Underground mining

There are presently three applications for new/ extended underground coal mines.

Proposed underground mines

Aberpergwm Colliery (Energybuild Ltd) in Neath port Talbot had planning permission for a 40+ million tonne underground (anthracite) coal mine approved in 2018. The Coal Authority offered the coal company, a license to extract coal in January 2022. Coal Action Network are currently considering legal action against the Coal Authority and Welsh Government for failing to stop the mine being licenced.

Lochinvar (Australian New Age Explorations) are applying for licences for an underground coking coal mine at Lochinvar in three sections, on the Scottish border. If constructed the company hopes to be producing coal until 2044. The first of the three areas would supply an average 1.4 million tonnes of coal each year.

Woodhouse Colliery proposed by West Cumbria Mining had its proposal for a new 1.78 million tonne per year underground coking coal mine off Whitehaven, Cumbria called in by the Secretary of State in 2021. The Planning Inspectorate ran a Public Inquiry in September 2021 and the report is expected to be given to the Secretary of State for Levelling Up, Housing and Communities, Michael Gove imminently.

Opencast coal extraction

There is currently an application to extend a previously operated mine at Glan Lash in Camarthanshire by Bryn Bach Coal.

The last existing opencast coal mine in the UK is Ffos-y-fran, operated by Merthyr (South Wales) Ltd in Merthyr Tydfil, it is widely reported to be due to close in October 2022.

UK steel producers

There are four major UK steel producers, half are using coking coal and produce much higher emissions that the two which recycle scrap steel.

Tata Steel
Port Talbot steel works, in Neath Port Talbot, Wales, is the second biggest UK single site emitter of carbon dioxide.[1] The plant uses coking coal to make steel in blast furnaces.

British Steel
Currently British steel’s Scunthorpe plant can use a maximum of 25% to 30% recycled content using Basic Oxygen Steel making. It currently uses coking coal.

Liberty

Liberty Steel, which has sites in Newport and in Tredegar, has said it aims to become a carbon-neutral steel producer by 2030. The site currently uses Electric Arc Furnaces and recycles scrap metal so does not use coking coal.

Celsa

Celsa’s Cardiff steelworks uses 100% recycled scrap steel in its products and so does not need coking coal.

For more details see our report Coal in Steel.

Power station closures

Ratcliffe on Soar power was given a contract to supply 411 MW to the grid from coal in 2022/23 at a Capacity Market auction in Feb 2022. Ratcliffe's owner Uniper plans to turn the power station into an incinerator for household waste and produce heat and electricity operational by 2026. It has secured planning permission.

Drax power station is supposed to have stopped burning coal this year. However it has offered that it could stay online until 2024 to the UK government.

EDF are closing their West Burton coal power station in September 2022.

Kilroot coal and oil power station in Northern Ireland is going to be converted to gas. It has been announced that Kilroot will stop consuming coal in September 2023.

Coal phase-out in the UK is expected by October 2024. Given that coal consumption in power stations is very low in the summer, the last generation could be April 2024.

Want to help in the fight against coal?

Reference

[1] The Coal Authority, Production and Manpower returns for three month period January to March 2020 and other sources.

Queries and media contact: info @ coalaction . org .uk (without spaces)

Share now:

Subscribe
Notify of
guest

0 Comments
Oldest
Newest Most Voted
Inline Feedbacks
View all comments

Never miss an update! Sign up to our Newsletter

OTHER STORIES

Lethal landscape: cuts to Ffos-y-fran mine restoration puts community at risk

16 years of opencast coal mining in Ffos-y-fran has generated colossal overburden mounds, also known as slag heaps or coal tips. There are three coal tips, with the third being the largest, and cumulatively accounting for 37 million cubic metres of colliery spoil, rocks, and soil…

We’re back in the Senedd giving oral evidence

We were invited for the second time to give oral evidence to the Climate Change, Environment, and Infrastructure Committee of the Welsh Parliament (Senedd) on 05th February 2025. We shared the panel with Haf, Director of FOE Cymru, to provide our opinion on the weaknesses, strengths…

Demand nature be restored to Ffos-y-fran opencast site

Merthyr (South Wales) Ltd mined for over a year illegally after planning permission for the Ffos-y-fran opencast coal mine ended in September 2022. During that year, it made record-breaking profits due to sanctions on Russia and other factors driving up the price of coal. But rather than using some of the profits from that ill-gotten coal…

We investigate mining company’s ‘missing’ millions

MSW claims “It was established that there are insufficient funds available to achieve the 2015 restoration strategy and therefore an alternative scheme is required.” (EIA Scoping Report, July 2024)… To our knowledge, there has been no evidence submitted by MSW that it cannot fund the full restoration it is contracted to undertake…

UK Government: is the left hand speaking to the right hand?

The UK Government launched a consultation on a limited review of the National Planning Policy Framework (NPPF) for 8 weeks from 30 July to 24 September 2024. The NPPF is an influential document that shapes planning decisions and priorities across England. It is periodically updated by the Government, following a public consultation…

We expose company’s misleading claims

Bryn Bach Coal Ltd attempts to present the anthracite coal it wishes to extract from an expansion of Glan Lash as a unique and scarce commodity that is needed for water filtration, bricks, and graphite, and would therefore be too valuable to burn. Yet, visiting Energybuild Ltd’s…

Major wins of 2024

Over the past year, we’ve secured some massive victories. By taking part in our digital actions, supporters sent over 26,000 messages to the UK Government, MPs, Welsh Senedd members, Councillors, and companies to help consign coal to the history books in the UK…

Disused Mine and Quarry Tips (Wales) Bill

The Disused Mine and Quarry Tips (Wales) Bill (‘the Bill’) was prompted by a series of coal tip landslides that occurred in Wales following storms’ Ciara and Dennis in 2020, including a major landslide of a disused coal tip in Tylorstown…

Under pressure: Europe’s largest mining investment conference

As B Labs doesn’t seem bothered was the public says, we asked supporters to contact other B Corps – who are effectively B Labs customers. Almost 20,000 emails were sent to over 60 B Corp status companies, asking them to take a stand with us…

CONNECT WITH US

Share now:

0
Would love your thoughts, please comment.x
()
x